Rebuilding of the Chute-à-Caron (Saguenay, Quebec) dam
Work to be performed: concrete stripping and drilling of dowels.
Period: 1996 to 2000
Challenges and special requirements:
- Work had to be performed on a vertical surface, since the dam was 200 feet high
- Two demolition and drilling teams had to work the same area simultaneously, but at different heights
- Some areas were hard to reach
- Precision drilling was required on vertical planes for the installation of the dam gates, and on sloped planes in the case of the discharge carrier
- Greater worker safety was to be ensured, and risks of falling were to be reduced, by using drilling platforms, thus eliminating the need to use scaffolds
- A working method entailing the use of a mini excavator on a platform made it possible to complete demolition work at times when proceeding manually was impossible in view of the risks of falling created by icy conditions
- The working methods used made it possible to move equipment more rapidly, compared to the traditional method requiring scaffolds.
Equipment used:
- CAT E120B excavator
- Hydraulic chisel
- Hydraulic mini excavator
- Hydraulic and pneumatic platforms
|